David Walton
I recently overheard a project manager talk about a 900-line MS Project plan. This was a business change project and the project was planned in detail for the next 12 months.
I have seen many examples of this type of very detailed planning for months in advance. In agile, there is a concept of rolling wave planning, but this concept has been around for a long time (pre-agile) and it is a very sensible approach to project planning.
There are three major problems with planning in detail for many months in advance, i.e.:
The better approach to project planning is ‘rolling wave planning”. Rolling wave planning means you plan in detail for what you know, which is usually the short to medium term. You do not plan in detail for what you don’t know or many months in advance.
As the project moves forward and there are fewer uncertainties, you extend the detailed plan. If we assume a simplistic example that we only know the detail of the project 3 months out, then we start by planning in detail for the first 3 months, i.e. detailed activities, and the remainder of the plan just contains approximate milestones.
After one month has elapsed we then plan in detail for the next month, i.e. the next wave so we now have one month that has passed and a rolling 3 months of a detailed plan.
In this contrived example, we always have a detailed 3 months plan and a high-level plan for the rest of the project because we only know what is likely to happen on the project 3 months out.
Let’s take an example. Imagine you are going on holiday in 2 weeks’ time. You know where you are going and what you are going to do. It is relatively easy then to develop a project plan that ‘delivers your holiday’. It is easy to do because you know a lot of information about your holiday and the key variables.
Now assume that you are going on holiday in a year’s time, but you don’t know where or even the exact timing of the holiday. It’s pointless planning in detail for this holiday in a year’s time. If you did plan it a year in advance and the destination or timing changed then you would have to redo the majority of the plan.
This is just the same concept as a business change project, i.e. plan for what you know in detail and plan at high level for what you don’t know.
It is a false notion that planning in detail for the whole project is a sign of careful and diligent planning by the project team. In reality, it is not only a waste of valuable project resources, but it actually devalues the project plan in the eyes of the project team and the stakeholders.
Using rolling wave planning builds confidence in the plan and is a more efficient use of scarce project resources.
Our products help you deliver successful change programmes and projects by always focusing on the overall business outcomes. Find out how our products can help you.
Tell me more Request a demoThe majority of PMOs that are, what we call ‘value-adding’ PMOs, will need to produce dashboards...
Read more >This blog takes you though the top 3 reports our clients produce....
Read more >The quality gate process is designed to ensure that projects can only pass through a gate if they ar...
Read more >